SDRC 9.4d Evidence Report: Produce learnings from energy storage and power electronic deployment

Posted on September 9th, 2016

The New Thames Valley Vision (NTVV) full bid submission [ Ref. 1] defines the Successful Delivery Reward Criteria (SDRC) that must be met in line with the project milestones. The full bid submission should be read in conjunction with the relevant change control documentation. The key topics covered within this report, as defined by the SDRC evidence requirements, […]

SDRC 9.8a (4) Evidence Report: LV Network Storage – ESMU Trials

Posted on September 9th, 2016

The New Thames Valley Vision (NTVV) full bid submission [Ref. 01] defines the Successful Delivery Reward Criteria (SDRC) that must be met in line with the project milestones. The full bid submission should be read in conjunction with the relevant change control documentation [Ref. 02 and Ref. 03]. The key topics covered within this report […]

SDRC 9.4c Evidence Report: Install 25 LV Connected Batteries

Posted on September 1st, 2016

The NTVV project has installed and connected 25 ESMUs as per the criteria defined in SDRC 9.4c. The installation of these devices will help Scottish and Southern Energy Power Distribution (SSEPD) and all other GB DNOs understand the benefits to network operation and capacity that these units may bring and also quantify the cost benefit […]

SDRC 9.4a – Discussion Document: Energy Storage and Power Electronics on the Low Voltage Distribution Network

Posted on September 1st, 2016

Power Electronics and Energy Storage The New Thames Valley Vision will deploy power electronics and storage (ESMU) to allow the existing network to respond more flexibly. This will maintain the network within the technical standards identified above whilst also maintaining or improving the efficiency of the network as customers change their energy behaviour as they […]