Library

SDRC 9.7 : Public Engagement

Posted on September 9th, 2016

This document meets the New Thames Valley Vision (NTVV) project deliverable in relation to SDRC 9.7, and outlines the next stages of development that will provide further information and learning from the project . The importance of distribution businesses conducting stakeholder engagement has been recognised in the regulation of energy networks. The NTVV project seeks to increase the […]

SDRC 9.5(a) Evidence Report: LV Customer Groups Presented

Posted on September 9th, 2016

SSEPD confirms that this criterion has been met. “Criterion: Establish a unique, reliable method for customer segmentation based on individual behavioural energy consumption. Produce first version of the universal customer categorisation vocabulary for DNOs. Evidence LV Customer Groups presented. The learning from the methods and techniques employed will be presented to enable third party application of these processes. […]

SDRC 9.3(c) : Public Engagement

Posted on September 9th, 2016

The NTVV project seeks to increase the understanding of engagement requirements for domestic, Small to Medium Enterprise (SME) and large business customers and considers the role of the distribution business in helping to achieve the low carbon transition plan. This document gives a narrative of and findings in relation to the activities of customer engagement in the specific […]

SDRC’s 9.3a & 9.3b Learning Report: Customer Engagement

Posted on September 9th, 2016

In the week commencing 27th February 2012 Thames Valley Vision (TVV) project met it’s first two key milestones or SDRC’s (successful delivery reward criteria). These SDRC’s were in relation to customer participation and engagement, The TVV project team organised and ran a Low Carbon Consumer Consortium Event and to run a Consumer Focus Group.  Further […]

SDRC 9.1c Evidence Report: Demand Side Response

Posted on September 9th, 2016

The importance of distribution businesses conducting Demand Side Response (DRS) has been recognised in the regulation of energy networks. The NTVV project seeks to better understand the needs of business customers, with particular focus on the role DSR can play in managing distribution network constraints. This document outlines the steps that were taken to establish […]

SDRC 9.8a 2 & 3: Demand Side Response Evaluation & Network Controlled Demand Side Response & Energy Efficiency

Posted on September 9th, 2016

The importance of distribution businesses conducting Demand Side Response (DRS) has been recognised in the regulation of energy networks. The NTVV project seeks to better understand the needs of business customers, with particular focus on the role DSR can play in managing distribution network constraints. This document outlines the steps that were taken to establish […]

SDRC 9.4(b) Evidence Report: Install 30 thermal energy storage devices

Posted on September 9th, 2016

SSEPD confirms that this criterion has been met through the installation of 30 energy storage devices (EMMAs) within domestic properties around Bracknell. This document provides details of the completion of the installation of 30 EMMAs, and presents the findings identified in line with the evidence criteria specified for the Successful Delivery Reward Criteria (SDRC). It is confirmed that: […]

SDRC 9.4d Evidence Report: Produce learnings from energy storage and power electronic deployment

Posted on September 9th, 2016

The New Thames Valley Vision (NTVV) full bid submission [ Ref. 1] defines the Successful Delivery Reward Criteria (SDRC) that must be met in line with the project milestones. The full bid submission should be read in conjunction with the relevant change control documentation. The key topics covered within this report, as defined by the SDRC evidence requirements, […]

SDRC 9.8a (4) Evidence Report: LV Network Storage – ESMU Trials

Posted on September 9th, 2016

The New Thames Valley Vision (NTVV) full bid submission [Ref. 01] defines the Successful Delivery Reward Criteria (SDRC) that must be met in line with the project milestones. The full bid submission should be read in conjunction with the relevant change control documentation [Ref. 02 and Ref. 03]. The key topics covered within this report […]

SDRC 9.8a Part 4: LV Network Energy Storage

Posted on September 1st, 2016

The EMMA units deployed in NTVV have a control algorithm especially configured for this project to adjust the amount of PV energy exported on to the network by diverting excess amounts to a conventional hot water storage tank via the customers existing immersion heater. The units, adjusted for this project: use a learning model of […]